Who Owns the Float

Oostewald van Niekerk
15th Dec, 2019

Float is not defined by the Joint Building Contracts Committee (JBCC) in any of their contract suites, nor by the FIDIC contract suits.  These are the two contracts most used by AGORA Quantity Surveyors.  However, float is a critical consideration when adjudicating extension of time claims.  The term float is used to refer to the time (normally in days) that an activity can be delayed before that activity becomes critical.  Float is built into the construction program by the contractor.  The question then arises: “Who owns the float?”

There are three possible owners of float:

  1. The Contractor
  2. The Client/Employer
  3. The Project

While it seems only fair to state that float belongs to the project, there is one brief period of time where float belongs to the contractor. The contractor decides how much float to assign to each activity in the project program.

The Contractor owns the float

The contractor created the float when he created the construction program, he determined the sequencing of the construction activities and thus created the float and he can directly impact the float based on his performance in executing the construction works.

A second argument for ownership by the contractor relates to risk. It is often assumed that the contractor carries the most risk relative to delays and are thus best suited to responsibly use the float.  Thus, the contractor created the float and should be permitted to use the float to mitigate delays experienced in zero float activities.

The Employer / Client owns the float

Ultimately everything belongs to the employer/client. He has paid for the services of the contractor which includes his program & sequencing of the works and thus the float that was built into the program. 

Just like the contractor the employer has certain risks if a project is delayed and should therefore be allowed to use the float in the program.  The JBCC clause 23.2 allows the contractor to claim an extension of time with an adjustment to the contract value.  This clause places the employer at risk to incur additional cost if he cannot use the float to mitigate this claim for an extension of time with cost.

The Project owns the float

The argument here is that the float in the program belongs to whoever uses it first. The key to this argument is that the parties uses the float in good faith. It is thus important that the contractor not claim for an item when float time exists. If float belongs to the project, all the float in the program should first be exhausted before an extension of time can be considered.

Conclusion

The subject of who owns the float is vague at best and construction contracts does not address the issue of float directly. The legal practice Kenney & Sam (KSlegal.com) offers a reasonable solution to the debate on ownership of float by suggesting adding a “joint ownership” and “non-sequestering” clause to the contract. Such a clause will provide that none of the parties specifically owns the float.

A generalized example of such a clause that the Quantity Surveyor can add to his Preliminaries and General Bill will be as follows:

Add

Clause 23.0 – REVISION OF THE DATE FOR PRACTICAL COMPLETION        

Clause 23.0 is amended by adding the following:

Float (time that an activity can be delayed before that activity becomes critical) including total project float, is not for the exclusive use of either party (The employer or his agents, or the contractor), but is jointly owned by all parties and is a resource available to and shared by the parties as needed to meet contract milestones including the contract practical completion date.  The Contractor will be open and honest about the float that was built into the program and shall not sequester float through extending activity duration to consume available float.



<< Back to News Index

EARLIER POSTS

Architect and Builder article feature Jul/Aug 2023| Effective Communication: The Cornerstone of Business Success

Architect and Builder article feature Jul/Aug 2023| Effective Communication: The Cornerstone of Business Success
6th Sep, 2023

The significance of protecting Heritage Buildings by means of Retrofitting

The significance of protecting Heritage Buildings by means of Retrofitting
1st Aug, 2023

What is Unbalanced Bidding and how to overcome it.

What is Unbalanced Bidding and how to overcome it.
22nd Jun, 2023

Professional Fees – A commentary on the Architectural (SACAP) Fee Guidelines

Professional Fees – A commentary on the Architectural (SACAP) Fee Guidelines
29th May, 2023

Beyond the Bottom Line: The “WHY” of Corporate Philanthropy.

Beyond the Bottom Line: The “WHY” of Corporate Philanthropy.
28th Apr, 2023

The Basic Principals of Contract Law in the Build Environment – As published by the South African Council for the Quantity Surveying Profession

The Basic Principals of Contract Law in the Build Environment – As published by the South African Council for the Quantity Surveying Profession
13th Apr, 2023

The Principal Agent under the JBCC Principal Building Agreement

The Principal Agent under the JBCC Principal Building Agreement
24th Mar, 2023

Building Information Modeling (BIM)

Building Information Modeling (BIM)
23rd Mar, 2023

When Two Become One: A Successful Company Integration

When Two Become One: A Successful Company Integration
17th Mar, 2023

The Role and Importance of Construction Project Management

The Role and Importance of Construction Project Management
10th Feb, 2023

COMMENTS

No comments.

Post a comment


You can use the following HTML tags: <a><br><strong><b><em><i><blockquote><pre><code><ul><ol><li><del>


CAPTCHA Image
Reload Image