Publications

Article Image | Agora Africa

Procedures of Dispute Resolution as regards to BCC PBA Edition 6.2

Jared Kisten
13th Apr, 2022

INTRODUCTION

Construction delays are any event that takes place during construction which would ultimately delay the completion date of the project and results in additional costs: for the client or property developer it means they would not be able to earn rental income when they planned to; for the contractor it means they have to be on the construction site for a longer period of time which means there might be additional costs associated with that. Who is responsible for these costs?

In construction we have two types of delays: an excusable delay – where the contractor would get additional costs due to delays beyond the contractors control and an inexcusable delay – resulting from the contractors’ default. Nevertheless, it is not always a straightforward exercise to determine who is responsible for the delay and associated costs and in some instances, disputes arise between the parties.

This series of blogs will explore the provisions of the JBCC PBA for dispute resolution, starting with an overview of the procedures provided for within the JBCC PBA.

DISAGREEMENTS

Where parties to the building agreement disagree regarding an action or inaction, or any other matter in terms of the agreement by either party, it is deemed to be a disagreement amongst the parties i.e., between the employer / principal agent / agent of the employer and the contractor. Typical cases of disagreements usually arise from adjudication of delay claims and adjustments to the contract value.

SETTLEMENT BY THE PARTIES

The JBCC PBA allows the parties a period of ten (10) working days to resolve disagreements by way of resolution in writing signed by each party. Where the disagreement is not resolved within the allowed time, the disagreement shall be deemed to be a dispute.

ADJUDICATION

Provisions for a disagreement to be referred to a dispute are allowed for the JBCC PBA. These provisions are as follows:

  1. A notice of adjudication must be issued by the referring party which gave the notice of disagreement. This notice must be referred within ten (10) working days following the period allowed for the disagreement to be resolved.
  2. The notice must clearly define the scope of the dispute and the relief which the referring party seeks.

The contract data [CD] makes provisions for a body (including their applicable rules) to be nominated for adjudication and arbitration in terms of the agreement. In most cases, the Association of Arbitrators (Southern Africa) is nominated as the adjudication and arbitration bodies for dispute resolution.

Where the parties have not made provision for an adjudication and / or arbitration nominating body in the contract data, the referring party has the right to choose a local recognised body to suggest one or more persons as an adjudicator or arbitrator and such nomination shall be binding on the parties as stipulated in the JBCC PBA.

Any ruling given by the adjudicator is immediately binding and the parties must implement the ruling. This shall remain in force and continue to be implemented unless overturned in arbitration. Either party may give notice to refer the dispute to arbitration. Such notice of dissatisfaction must be issued to the adjudicator and the opposing party within ten (10) working days following the adjudicators ruling (determination).

ARBITRATION

According to the JBCC PBA, the dispute will be resolved by arbitration and not adjudication where the referring party failed to comply with procedures of adjudication and / or the referral of the adjudicator’s determination by either party.

The arbitrator will conduct a pre-arbitration meeting to determine the following for the arbitration proceedings:

Appointment of the arbitrator

The parties must acknowledge the appointment of the nominated arbitrator. The arbitration fees must also be agreed upon i.e., the parties may agree to split the arbitrators’ fees and other costs of arbitration on a 50/50 basis (until final reward in relation to costs has been made).

Confirmation that arbitral disputes exists

The parties must confirm the arbitral dispute, the scope thereof, and that the arbitrator has jurisdiction to decide the dispute.

The rules for the arbitration

The rules of the arbitration must be agreed. It is usually the rules of the nominating body i.e., the Rules for the Conduct of Arbitrations for the Association of Arbitrators (Southern Africa) (2018 Edition).

 

Arbitration Timetable

PARTY

STEP IN THE PROCEEDINGS

Claimant

Claimant to file its Statement of Claim

Respondent‎‎‏‏‎ ‎‏‏‎ ‎‏‏‎ ‎ ‎‏‏‎ ‎‏‏‎ ‎

Respondent to file its Statement of Defence

Claimant

Claimant to file its Replication (if any)

Respondent

Respondent to file Rejoinder (if any)

Claimant

Claimant to file its factual witness statements (with expert witness statements, if any)

Respondent

Respondent to file its factual witness statements (with expert witness statements, if any)

Claimant

Claimant to file its replying witness statements (if any)

All

Hearing

Arbitrator

Determination

The parties must agree to the arbitration timetable and the dates set out therein. The table below is a typical example of the dates to be determined for each step in the proceedings.

 

Service of pleadings and documents

The parties must agree on the service of pleadings and documents i.e., by email and / or hard copy.

Documents

Witness statements to stand as evidence (under oath) in chief and any additional evidence over and above that set out in the witness statements must be confirmed.

Witness statements

The parties must confirm the service of witness statements i.e., the factual witness statements (including rebuttal statements), as supplemented if applicable, will stand as evidence in chief, subject to the witness confirming the contents of the statement under oath at which time every witness may clarify any errors in the statement. The parties may also confirm if the Arbitrator shall have a general discretion to allow either party to lead additional evidence over and above that set out in the witness statements.

Interlocutory applications

The procedures of interlocutory applications must be agreed between the parties. For example, A Party (the “Applicant”) shall be entitled to set out in an email addressed to the Arbitrator and the other Party its application, the  basis  therefore  and  any  representations  or  submissions  it wishes to make (the “Application”) and The other Party will be entitled to respond within one week or such  other  time  as  the  Arbitrator  should  allow,  by  email addressed  to  the  Arbitrator  and  the  Applicant  setting  out  its opposition, the basis therefore and  opposition, any  representations  or submissions it wishes to make (the “Opposition”).

The Arbitrator will be entitled to make any ruling having regard to the Application and the Opposition only and without oral hearing. Should the Arbitrator require a hearing or further representations or written submissions he will advise the Parties and issue directives accordingly.

Bundle

The collation of indexed and paginated bundles must be determined and agreed by the parties. The availability of the bundles must also be confirmed i.e., 10 days before the hearing.

Venue and recording of proceedings

A venue or a virtual platform i.e., MS Teams must be determined and one of the parties will be responsible for arranging the transcription services (if required).

Handing down of the award

The arbitrators award shall be final and binding on the parties in terms of the JBCC PBA.

MEDIATION

Adjudication and arbitration may be referred by agreement between the parties to mediation at any time during the proceedings. Where a dispute is referred to mediation, the provisions relating to adjudication and / or arbitration shall be deemed to be suspended.

 

CONCLUSION

The procedures of dispute resolution in the JBCC PBA are clearly defined and provides a structured path towards resolving disputes. The contract, together with various case studies available is referred to by an adjudicator / arbitrator in their determination and award.

This series will continue by exploring each of the procedures mentioned above in more detail and how each of them have been dealt with and applied previously in some cases.

 

 



<< Back to News Index

EARLIER POSTS

Construction Consulting Tendering and Its Challenges in South Africa: Winning Business While Facing Challenges

Construction Consulting Tendering and Its Challenges in South Africa: Winning Business While Facing Challenges
20th Mar, 2024

Beyond the Bottom Line: The “WHY” of Corporate Philanthropy.

Beyond the Bottom Line: The “WHY” of Corporate Philanthropy.
14th Feb, 2024

The importance of tax planning and having a tax planning strategy for South African businesses within the Quantity Surveying industry

The importance of tax planning and having a tax planning strategy for South African businesses within the Quantity Surveying industry
2nd Feb, 2024

Professional Fees Series: Commentary on the 2015 Guideline Tariff of Professional Fees for Quantity Surveyors

Professional Fees Series: Commentary on the 2015 Guideline Tariff of Professional Fees for Quantity Surveyors
9th Jan, 2024

The Workplace Chronicles

The Workplace Chronicles
17th Nov, 2023

Architect and Builder article feature Jul/Aug 2023| Effective Communication: The Cornerstone of Business Success

Architect and Builder article feature Jul/Aug 2023| Effective Communication: The Cornerstone of Business Success
6th Sep, 2023

The significance of protecting Heritage Buildings by means of Retrofitting

The significance of protecting Heritage Buildings by means of Retrofitting
1st Aug, 2023

What is Unbalanced Bidding and how to overcome it.

What is Unbalanced Bidding and how to overcome it.
22nd Jun, 2023

Professional Fees – A commentary on the Architectural (SACAP) Fee Guidelines

Professional Fees – A commentary on the Architectural (SACAP) Fee Guidelines
29th May, 2023

The Basic Principals of Contract Law in the Build Environment – As published by the South African Council for the Quantity Surveying Profession

The Basic Principals of Contract Law in the Build Environment – As published by the South African Council for the Quantity Surveying Profession
13th Apr, 2023